The supervising electrician, Steve, dropped in.

First he inspected the inverter and other things hung on Day 2. He recommended a "gutter" to route all the wiring under the equipment, rather than a bunch of conduits.

Next he checked out the breaker box. Our breaker was rather full, we only had one open circuit. He was able to move one wire and then replace a single switch with a double that fit in the same slot. This freed up the two adjacent slots that he needed.

He was not there long, and no other work was done, but I am including this for completeness.