Sarah and Ron returned. They worked on another site in the morning and came by after lunch to work on my project. They installed the gutter that Steve recommended. You can see it on the bottom of the picture, with all the other devices attaching conduits to it.
They also ran nearly all the DC conduits. You can see the conduit coming down into the DC disconnect. This included coming down the very high south wall and under the house.
They are now predicting they they will finish with two more work days.
Total on-Site Labor Hours to date:
Day 1: 8 Hours
Day 2: 14 Hours
Day 3: 1 Hour
Day 4: 8 Hours
Total: 31 Labor Hours
Wednesday, November 14, 2007
Day 4 of Solar Install